Planned Maintenance Safety Inspection
- Inspection
of fan and coupling guards for corrosion and security, making sure rotating
parts have been well guarded ie no loose or missing bolts.
- Manually
check main pump shaft for radial and axial movement. This can indicate
bearing wear and could cause mechanical seal failure.
- Check
for free rotation of pump, tightness in wear rings, bearing failure
or looseness.
Alignment of pump and motor.
- Coupling
Condition
- Mechanical
seal and flange leakage.
- Vibration
trending of all ball/roller bearings. This will indicate condition of
bearings, bad alignment and pump stress due to pipe stress.
- Relief
valve condition and settings.
A summary/priority
chart will be issued to the Maintenance Manager along with individual
pump reports.
Commissioning
of New Plant
If new pumping
equipment is installed we can commission the equipment independently from
the main contractor.
We will:
- Make sure
there is no pipe stress, base plates are fitted correctly and that they
are adequate for the job.
- Realign
pump to motor.
- Ensure
no excessive vibration.
- The pump
has been built correctly with no leaking mechanical seals or overheating
of bearings.
All work undertaken
will come with a full report.